Natural disaster events and allowable time limits

The following information provides details of recent natural disaster events and allowable time periods to incur expenditure and submit claims for reimbursement through Victoria’s Natural Disaster Financial Assistance (NDFA) scheme.

Any costs incurred after these deadlines will be deemed ineligible for reimbursement. Please note that these timelines allow the Victorian Government to comply with Commonwealth Government timelines for acquittal and audit requirements.

Natural Disaster Event AGRN Eligible categories and measures  Deadline to submit formal 'certified' estimate or market price** When eligible expenses can be incurred Lodgement of claims Financial year lodgement date Registered Councils impacted
Flood and Storm, 13 December 2018 830 Category A Measures           
    Emergency assistance for individuals  - From event date up to 31/3/19* Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Alpine, Buloke, Indigo, Loddon, Moorabool, Wangaratta, Wodonga, Northern Grampians, Moira
    Relief and Recovery Centres - From event date up to 31/3/19* Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Alpine, Buloke, Indigo, Loddon, Moorabool, Wangaratta, Wodonga, Northern Grampians, Moira
    Counter disaster operations - Activities to be undertaken immeditaley prior to, during, and as soon as possible after the event (but before 31/3/19*) Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Alpine, Buloke, Indigo, Loddon, Moorabool, Wangaratta, Wodonga, Northern Grampians, Moira
    Personal and Financial Counselling - From event date up to 31/3/19* Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Alpine, Buloke, Indigo, Loddon, Moorabool, Wangaratta, Wodonga, Northern Grampians, Moira
Flood and Storm, 13 December 2018 830 Category B Measures           
    Emergency works and immediate reconstruction works - From event date up to 31/3/19 Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Alpine, Buloke, Indigo, Loddon, Moorabool, Wangaratta, Wodonga, Northern Grampians, Moira
    Counter disaster operations for the protection of the general public.  - Activities to be undertaken immeditaley prior to, during, and as soon as possible after the event (but before 31/3/19*) Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Alpine, Buloke, Indigo, Loddon, Moorabool, Wangaratta, Wodonga, Northern Grampians, Moira
    Essential public asset reconstruction works
1/03/2020
From date of approval to 30/6/21 Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 (if formal certified estimate/market price is received early)
19-20
20-21
Alpine, Buloke, Indigo, Loddon, Moorabool, Wangaratta, Wodonga, Northern Grampians, Moira
Flood and Storm, 13 December 2018 830 Category C Measures  N/A N/A N/A N/A N/A
Flood and Storm, 13 December 2018 830 Category D Measures N/A N/A N/A N/A N/A
 
Rosedale Bushfire commencing 4 January 2019 837 Category A - Measures           
    e) removal of debris from residential properties to make them safe and habitable  - From event date up to 30/04/19* Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Wellington
    f) extraordinary counter disaster operations - From event date up to 30/04/19* Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 18-19 Wellington
Rosedale Bushfire commencing 4 January 2019 837 Category B - Measures           
    a) Counter Disaster Operations for the protection of the general public - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Wellington
    b) Emergency Works for essential public assets - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Wellington
    c) Immediate reconstruction works for essential public assets  - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Wellington
    d) Essential public asset reconstruction works in which costs are estimated 1/03/2020 From date of approval to 30/6/21 Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 (if formal certified estimate/market price is received early)
19-20
20-21
Wellington
Rosedale Bushfire commencing 4 January 2019 837 Category C - Measures  N/A N/A N/A N/A N/A
Rosedale Bushfire commencing 4 January 2019 837 Category D - Measures  N/A N/A N/A N/A N/A
 
 
Timbarra  Bushfires commencing 16 January  2019 852 Category A Measures           
    a) emergency food, clothing or temporary accommodation  - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 East Gippsland
    b) repair and replacement of essential items of furniture and personal effects  - N/A N/A N/A N/A
    c) essential repairs to housing  - N/A N/A N/A N/A
    d) demolition or rebuilding to restore housing to a habitable condition  - From event date up to 16/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 East Gippsland
    e) removal of debris from residential properties to make them safe and habitable  - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 East Gippsland
    f) extraordinary counter disaster operations - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 East Gippsland
    g) personal and financial counselling  - From event date up to 16/01/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 East Gippsland
Timbarra  Bushfires commencing 16 January  2019 852 Category B Measures           
    a) Counter Disaster Operations for the protection of the general public - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 East Gippsland
    b) Emergency Works for essential public assets - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 East Gippsland
    c) Immediate reconstruction works for essential public assets  - From event date up to 30/04/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 East Gippsland
    d) Essential public asset reconstruction works in which costs are estimated 1/03/2020 From date of approval to 30/6/21 Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 (if formal certified estimate/market price is received early)
19-20
20-21
East Gippsland
Timbarra  Bushfires commencing 16 January  2019 852 Category C - Measures  - N/A N/A N/A N/A
Timbarra  Bushfires commencing 16 January  2019 852 Category D - Measures  - N/A N/A N/A N/A
 
Thomson Catchment   Bushfires commencing 25 January  2019 854 Category A Measures           
    a) emergency food, clothing or temporary accommodation  - N/A N/A N/A N/A
    b) repair and replacement of essential items of furniture and personal effects  - N/A N/A N/A N/A
    c) essential repairs to housing  - N/A N/A N/A N/A
    d) demolition or rebuilding to restore housing to a habitable condition  - From event date up to 25/01/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 Baw Baw, Latrobe and Wellington
    e) removal of debris from residential properties to make them safe and habitable  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe and Wellington
    f) extraordinary counter disaster operations - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe and Wellington
    g) personal and financial counselling  - From event date up to 25/01/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 Baw Baw, Latrobe and Wellington
Thomson Catchment   Bushfires commencing 25 January  2019 854 Category B Measures           
    a) Counter Disaster Operations for the protection of the general public - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe and Wellington
    b) Emergency Works for essential public assets - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe and Wellington
    c) Immediate reconstruction works for essential public assets  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe and Wellington
    d) Essential public asset reconstruction works in which costs are estimated 1/03/2020 From date of approval to 30/6/21 Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 (if formal certified estimate/market price is received early)
19-20
20-21
Baw Baw, Latrobe and Wellington
Thomson Catchment   Bushfires commencing 25 January  2019 854 Category C - Measures  N/A N/A N/A N/A N/A
Thomson Catchment   Bushfires commencing 25 January  2019 854 Category D - Measures  N/A N/A N/A N/A N/A
 
Victoria Bushfires and Storms commencing 30  January  2019 859 Category A Measures           
    a) emergency food, clothing or temporary accommodation  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Campaspe, Mitchell
    b) repair and replacement of essential items of furniture and personal effects  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw
    c) essential repairs to housing  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw
    d) demolition or rebuilding to restore housing to a habitable condition  - From event date up to 30/01/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 Baw Baw, Latrobe, Wellington
    e) removal of debris from residential properties to make them safe and habitable  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe, Wellington, Campaspe, Cardinia, Macedon Ranges, Mitchell, Sth Gippsland.
    f) extraordinary counter disaster operations - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe, Wellington, Campaspe, Cardinia, Macedon Ranges, Mitchell, Sth Gippsland.
    g) personal and financial counselling  - From event date up to 30/01/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 Baw Baw, Latrobe, Wellington
     h) Community Recovery Officer - From event up to 30/6/21* Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 19-20, 20-21 Baw Baw, Latrobe, Wellington 
(DHHS to claim costs associated with this role)
Victoria Bushfires and Storms commencing 30  January  2019 859 Category B Measures           
    a) Counter Disaster Operations for the protection of the general public - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe, Wellington, Campaspe, Cardinia, Macedon Ranges, Mitchell, Sth Gippsland.
    b) Emergency Works for essential public assets - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe, Wellington, Campaspe, Cardinia, Macedon Ranges, Mitchell, Sth Gippsland.
    c) Immediate reconstruction works for essential public assets  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw, Latrobe, Wellington, Campaspe, Cardinia, Macedon Ranges, Mitchell, Sth Gippsland.
    d) Essential public asset reconstruction works in which costs are estimated 1/03/2020 From date of approval to 30/6/21 Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 (if formal certified estimate/market price is received early)
19-20
20-21
Baw Baw, Latrobe, Wellington, Campaspe, Cardinia, Macedon Ranges, Mitchell, Sth Gippsland.
Victoria Bushfires and Storms commencing 30  January  2019 859 Category C - Measures  N/A N/A N/A N/A N/A
Victoria Bushfires and Storms commencing 30  January  2019 859 Category D - Measures  N/A N/A N/A N/A N/A
               
Victorian Bushfires commencing 28 February 2019 846 Category A Measures           
    a) emergency food, clothing or temporary accommodation  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw,  Cardinia, East Gippsland,  Latrobe,  South Gippsland,  Wellington, 
    b) repair and replacement of essential items of furniture and personal effects  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Baw Baw,  Cardinia, East Gippsland,  Latrobe,  South Gippsland,  Wellington, 
    c) essential repairs to housing  - From event date up to 28/02/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19,  19-20 Baw Baw,  Cardinia, East Gippsland,  Latrobe,  South Gippsland,  Wellington, 
    d) demolition or rebuilding to restore housing to a habitable condition  - From event date up to 28/02/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
    e) removal of debris from residential properties to make them safe and habitable  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
    f) extraordinary counter disaster operations - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
    g) personal and financial counselling  - From event date up to 28/02/20* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19, 19-20 Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
     h) Community Recovery Officer - From event up to 30/6/21* Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. 19-20, 20-21 Baw Baw,  Cardinia, East Gippsland,  Latrobe,   Wellington (DHHS to claim costs associated with this role)
Victorian Bushfires commencing 28 February 2019 846 Category B Measures           
    a) Counter Disaster Operations for the protection of the general public - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
    b) Emergency Works for essential public assets - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
    c) Immediate reconstruction works for essential public assets  - From event date up to 30/05/19* Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
    d) Essential public asset reconstruction works in which costs are estimated 1/03/2020 From date of approval to 30/6/21 Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 18-19 (if formal certified estimate/market price is received early)
19-20
20-21
Alpine, Baw Baw, Benalla, Cardinia, East Gippsland, Indigo, Latrobe,  Mansfield, Mitchell, Murrindindi, South Gippsland, Towong, Wangaratta, Wellington, Yarra Ranges
Victorian Bushfires commencing 28 February 2019 846 Category C - Measures  N/A N/A N/A N/A N/A
Victorian Bushfires commencing 28 February 2019 846 Category D - Measures  N/A N/A N/A N/A N/A
               
Eastern Victoria Storms commencing 10 July 2019 874 Category A Measures           
    a) emergency food, clothing or temporary accommodation  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    b) repair and replacement of essential items of furniture and personal effects  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    c) essential repairs to housing  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    d) demolition or rebuilding to restore housing to a habitable condition  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    e) removal of debris from residential properties to make them safe and habitable  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    f) extraordinary counter disaster operations - From event date up to 11/10/19 * Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 Baw Baw,  Mornington Peninsula. 
    g) personal and financial counselling  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
     h) Community Recovery Officer - N/A Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. N/A N/A
Eastern Victoria Storms commencing 10 July 2019 874 Category B Measures           
    a) Counter Disaster Operations for the protection of the general public - From event date up to 11/10/19 * Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 Baw Baw,  Mornington Peninsula. 
    b) Emergency Works for essential public assets - From event date up to three months the essential public asset becomes accessible *** Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 Baw Baw,  Mornington Peninsula. 
    c) Immediate reconstruction works for essential public assets  - N/A N/A N/A N/A
    d) Essential public asset reconstruction works in which costs are estimated - N/A N/A N/A N/A
Eastern Victoria Storms commencing 10 July 2019 874 Category C - Measures  - N/A N/A N/A N/A
Eastern Victoria Storms commencing 10 July 2019 874 Category D - Measures  - N/A N/A N/A N/A
               
Eastern Victoria Storms and Floods commencing 8 August 2019 873 Category A Measures           
    a) emergency food, clothing or temporary accommodation  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    b) repair and replacement of essential items of furniture and personal effects  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    c) essential repairs to housing  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    d) demolition or rebuilding to restore housing to a habitable condition  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    e) removal of debris from residential properties to make them safe and habitable  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
    f) extraordinary counter disaster operations - From event date up to 08/11/19 * Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 Baw Baw,  Bass Coast, South Gippsland. 
    g) personal and financial counselling  - N/A Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. N/A N/A
     h) Community Recovery Officer - N/A Regular intervals, individual claims should be submitted within 8 weeks after the works/services being completed and not exceed $500,000. N/A N/A
Eastern Victoria Storms and Floods commencing 8 August 2019 873 Category B Measures           
    a) Counter Disaster Operations for the protection of the general public - From event date up to 08/11/19 * Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 Baw Baw,  Bass Coast, South Gippsland. 
    b) Emergency Works for essential public assets - From event date up to three months the essential public asset becomes accessible *** Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 Baw Baw,  Bass Coast, South Gippsland. 
    c) Immediate reconstruction works for essential public assets  - From event date up to three months the essential public asset becomes accessible *** Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 Baw Baw,  Bass Coast, South Gippsland. 
    d) Essential public asset reconstruction works in which costs are estimated 1/03/2021 From date of approval to 30/6/22 Regular intervals, individual claims should not exceed $500,000 with the final claim submitted within 8 weeks after the works/services being completed. 19-20 (if formal certified estimate/market price is received early)
20-21
21-22
Baw Baw,  Bass Coast, South Gippsland. 
Eastern Victoria Storms and Floods commencing 8 August 2019 873 Category C - Measures  - N/A N/A N/A N/A
Eastern Victoria Storms and Floods commencing 8 August 2019 873 Category D - Measures  - N/A N/A N/A N/A

* Councils required to advise DTF (via Regional Roads Victoria) if further time is needed at least 2 weeks prior to the end of the allowable time period for Category A expenditure. 

For Category B Emergency and Immediate Works, Councils required to advise VicRoads at least 2 weeks prior to the end of the allowable time period as per Guideline 1: Claims and eligibility for essential public assets page 7. 
For Essential public asset Reconstruction works, Councils required to advise VicRoads, 3 months prior to the end of the allowable time period, as per Councils required to advise VicRoads as per Guideline 1: Claims and eligibility for essential public assets page 7.

** Estimates (best estimates) are to be updated in the Automated Claims Management System (ACMS) at a minimum on a quarterly basis, for all outlays.

*** For the purposes of determining when the three month timeframe for completing emergency and immediate reconstruction works starts and finishes, an EPA is considered to be ‘accessible’ from the time when:

  • the disaster is no longer occurring (e.g. flood waters have receded or a bushfire is out/under control) and the site of the damaged asset can be safely accessed by reconstruction workers, or
  • the state or a council has capacity to undertake the required restoration works. In this situation, the state/council must be able to demonstrate they have made a reasonable attempt to commence works as soon as the disaster was no longer occurring (as per the point above) but was not able because of either:
    • competing reconstruction priorities associated with a significant program of works caused by a severe disaster or multiple disasters, or
    • the unavailability of specialised equipment/resources.

Note that Councils are required to provide supporting documentation that demonstrates date of access to each of the essential public assets when lodging a claim.

Reviewed 23/10/2019